Preparation of design documentation for the reconstruction of the existing fly ash silo and installation of the equipment for the transport and batching of fly ash in the cement mill within the complex of Titan Cement Factory Kosjerić – Kosjerić

Realization: 2010

According to the specified operation technology, the scope of the Project for the reconstruction of the existing fly ash silo and installation of the equipment for the transport and batching of fly ash in the cement mill can be divided into five units:

1.SILO FILLING SYSTEM - new system, design and workshop documentation

2.EXISTING SILO - modification and extension, design and workshop documentation

3.BATCHING (MEASURING) EQUIPMENT - new equipment procured, functional and technological connection, design and workshop documentation

4.ASH TRANSPORT SYSTEM - use of procured equipment and design of missing equipment, design and workshop documentation

5.DEDUSTING - locally extraction and filtration of waste air from the process.

Complete technical documentation includes mechanical, construction and electrical designs.