Final design for reconstruction of tracks no.5 and no.6 in Belgrade Center station together with temporary connection from Pančevo direction

Works on construction of the main station through tracks No. 5 and No. 6 and their temporary connections with the left track on Pančevački Most were entrusted to the Contractor (''Energorprojekt Visokogradnja''), while the Institute of Transportation CIP together with the ''Serbian Railways'' PE was engaged in supervision works. The works also included equipping the segment of the platform and subway for passenger approach.

Tracks were put into operation after providing all relevant approvals.

Completion of these works will enable establishment of regular traffic flow on the double track railway line on Batajnica-Pančevo, Batajnica-Resnik and Resnik-Pančevo sections within the ''Beovoz'' transport system.
For the first time, a new construction technology was implemented in Serbia. It included placement of track on concrete slab by using the state-of-the-art track fastening system, PANDROL VANGUARD type, that enables absorption of noise and vibration and provides protection for station and other residential buildings.

After completion of works, experts from PANDROL company performed inspection and verified that works and installation of track fastening sets were carried out according to high quality standards