Final rehabilitation design of tramway tracks and OCS in Vojvode Mišića Boulevard

Realization: 2007

The prepared technical documentation included: geotechnical documentation for the final design level, preliminary and final civil engineering designs for substructure and permanent way, pavement, sidewalks and parking areas, including sewage network, reconstruction of tramway OCS, control and heating of points, traffic signaling and equipment, lighting system, protection of hot water pipeline and cathodic protection. The design documentation also included geodetic setting out design, work methodology design and tender documents.

The design has accepted the fact that this Boulevard is used for traffic running from Ibarska Main Road as well as significant number of level crossings with the tram line that enable passage for users of business complex across the Belgrade Fair.

The studied section is 1703 m long (left track), i.e. 1700 m long (right track). The overall length of tram tracks as specified in the design is 3403 m.

The design also included tramway loop near Gospodarska Mehana.