Technical and Designer supervision of rehabilitation works on the Pančevački road-railway bridge over the Danube River, Phase 1

Works on railway structures over the flood areas on the left bank of the Danube River included installation of additional members to reinforce structures over flood areas and complete renewal of anti-corrosion protection (sand blasting to a grade of Sa 21/2 and applying 4 protective coatings on structural member surfaces).

- works on central bridge structure included replacement of damaged structural members with new ones (150 t of steel installed), renewal of anti-corrosion protection on external surfaces of structural members and internal surfaces of the lower chord of main lattice girders (including sand blasting to a grade of Sa 21/2 and applying protective coatings)